✅ Ready work only — committable plan (authorized + in-progress). The rest of the backlog is below, grouped by what's blocking it.
20 jobs ordered by delivery due date then promised date then profit. Six overdue deliveries (3351, 3361, 3393, 3389, 3381, 3345) are pushed to the top. Jered takes the high-skill diff assembly (3345) and cam/water pump (3184); Charlie handles the large engine block (3020) and brake/A/C work; Sean fills with shorter authorized jobs and holds unauthorized work pending callbacks. Four unauthorized jobs (3351, 3361, 3406, 3407, 3411) need customer approval calls before work begins. WO 3389 is flagged as a suspected comeback due to a UV leak recheck. Appointments 3409 and 3335 sit at the bottom as Charlie is the only eligible tech and both are uninspected/unapproved.
2026-06-24
· 9 job(s) · 32.0h · $27,642
Charlie Spirka
WO 3409
6.0h
pending appr.
due 2026-06-22
— Appointment 2026-06-22 (past, awaiting floor), not authorized/inspect status; Charlie is sole eligible tech — callback needed for approval.
Charlie Spirka
WO 3351
3.4h · $766
pending appr.
due 2026-06-19
— Delivery was 2026-06-17, most overdue job on the board; Charlie has strong rear-brakes/brake history — callback needed to get authorization before starting.
Jered Verhaeghe
WO 3361
3.0h · $466
pending appr.
due 2026-06-22
— Delivery was 2026-06-16, oldest due date overall; needs customer approval callback to unlock.
Sean Lake
WO 3393
3.3h · $800
due 2026-06-19
— Delivery 2026-06-17, authorized, oil+coolant hose work; spreads load to Sean while Jered/Charlie handle other overdue jobs.
Jered Verhaeghe
WO 3389
4.4h · $1,162
due 2026-06-19
— Delivery 2026-06-17, authorized; tie rod + UV leak recheck suits an A-tech, Jered balances load here.
Charlie Spirka
WO 3381
2.6h · $1,152
due 2026-06-19
— Delivery 2026-06-17, authorized; A/C evac+recharge and actuator work fits Charlie's skill set.
Jered Verhaeghe
WO 3345
4.6h · $9,567
due 2026-06-19
— Delivery 2026-06-18, authorized, highest-value diff assembly job ($9,567/15.7h); Jered is strongest at diff service.
Sean Lake
WO 3369
4.2h · $1,195
due 2026-06-19
— Delivery 2026-06-18, authorized; thermostat/water pump/cooling service, good B-tech work to spread load.
Sean Lake
WO 3020
0.5h · $12,534
due 2026-06-19
— Delivery 2026-06-19, authorized, high-value engine block assembly ($12,534); A-tech needed, Charlie takes this large job.
🔁 Suspected comebacks (AI-detected — confirm to flag)
WO 3389
— Work includes 'Add Dye & Recheck for Engine Oil Leaks (UV Leak Detection)' — a recheck implies a prior leak diagnosis or repair was done and the concern has returned or not been resolved.
⚠️ Started but won't fully fit this window (overflow to next week):
WO 3381 (1.8h left), WO 3345 (11.1h left), WO 3020 (21.4h left)
⚠️ Not placed — no capacity left in the window (or no eligible tech): 3335, 3326, 3416, 3410, 3411, 3400, 3406, 3417, 3407, 3184, 3289.
These stay in the regular backlog/carryover.
📋 Pipeline — not ready to schedule
(34 jobs · needs action to become schedulable)
📅 Booked appt (not yet authorized) · 20 job(s)
WO 3402
7.2h · $1,759
due 2026-06-22
⛔ On hold · 7 job(s)
WO 2206
3.0h · $4,981
due 2026-06-29
WO 2733
3.0h · $3,273
due 2026-06-29
WO 2884
3.2h · $1,708
due 2026-06-29
WO 2887
8.6h · $2,407
due 2026-06-29
WO 2997
3.4h · $1,840
due 2026-06-29
WO 3356
50.9h · $11,004
due 2026-06-19
WO 3372
24.6h · $7,120
due 2026-06-22
⏸ Awaiting approval · 5 job(s)
WO 3390
3.5h · $1,196
due 2026-06-19
WO 3387
7.2h · $2,102
due 2026-06-19
WO 3396
5.4h · $1,413
due 2026-06-18
✋ Held by SA · 2 job(s)
WO 2992
10.2h · $4,810
due 2026-06-19
WO 3212
5.4h · $1,445
due 2026-06-22
Action: release holds, finish triage, or call for approvals — then they move into the schedule. (Or hit Full projection above to see them laid across the week.)